DC in SEZ will Allow Import of Sand and Soil from DTA after Checking
for Compliance with Environment Regulations
[SEZ Instruction No. 111
dated 29 August, 2022]
Subject: Permission for
domestic procurement of restricted items (sand and soil) by developers / co-developers
/ units for infrastructural development / construction activities inside the Special
Economic Zones (SEZs)
I am directed to refer
to the subject cited above and to state that as per Section 2(m) of the SEZ Act,2005,
supplying goods, or providing services, from the Domestic Tariff Area (DTA) to a
Unit or Developer amounts to “export”. The export policy of Directorate General
of Foreign Trade (DGFT) as regards sand and soil which are primarily required for
construction activities and infrastructure development is ‘restricted’. [n terms
of fourth proviso of sub-rule (l) of Rule 27 of the SEZ Rules, 2006, for supply
of Restricted items by a DTA unit to SEZ developer or unit, the DTA unit may supply
such items to a SEZ developer or unit for setting up infrastructure facility or
for setting up of a unit and it may also supply raw materials to SEZ unit for undertaking
a manufacturing operation except refrigeration, cufting,
polishing and blending, subject to the prior approval of Board of Approval (BoA).
2. Department of Commerce
(DoC) has been receiving proposals for supply of raw materials
(primarily sand / soil) required for infrastructure development / construction in
the zone and the same were being placed before the BoA
for necessary permission as per the rule position stipulated above. The BoA has allowed such procurements from time to time subject
to the condition that the allowed items are actually used by the developer / unit,
as the case may be and applicable environmental / other statutory obligations are
duly complied with.
3. During the interactive
sessions held on the operational issues faced by the SEZs in the during the lock-down
imposed for the Covid- 19 pandemic, the developers / co-developers / units in SEZs
had put forth the request to allow them procurement of sand / soil for internal
consumption without obtaining approval from BoA so that
they can carry out the construction activities without delay, as the meeting of
the BoA is held at a frequency of once in every two months.
Accordingly, in order to facilitate the industry, a Circular was issued to all DCs
with the approval of the Hon’ble CIM on 18.05.2020 delegating the powers to the
Development Commissioner (DC) to allow procurement of sand and soil from DTA for
construction activities subject to the following conditions:
(i) Items allowed are
actually used by the unit.
(ii)
Fulfillment of
safeguards and Standard operating Procedures imposed by MHA (in view of lockdown
situation and restrictions prevalent at that time).
(iii)
Environmental obligations prescribed by the
MoEF&CC / State Pollution Control Board are met; and
(iv)
Post facto ratification by BoA, whenever the next meeting is convened
4. In light of the said
Circular, the DCs are considering such requests raised by the units / developers
from time-to-time and granting approval as per the delegation. The cases are then
received for post-facto ratification by the BoA as per
condition no. (iv) laid down in the said Circular.
5. Since, construction
activity is of a routine nature of infrastructure development and the same can be
carried out under the close observation of the DC, it was proposed that the same
may permanently be delegated to the Unit Approval Committee (UAC) to simplify the
procedure and formalities subject to the condition that the items are actually used
in the SEZ.
6. After detailed consultations
with the Department of Revenue (DoR), DGFT and the Legislative
Department, the matter was placed before the BoA in its
I 11th meeting held on 28.07.2022. The Board, after deliberations, decided to delegate
its power under Section 9(4) of the SEZ Act, 2005 to the DC to allow supply of sand
and soil (which is restricted item, as per export policy) by DTA unit to Special
Economic Zone developer or unit for the purpose of construction or setting up of
an infrastructural facility subject to the condition that the items are actually
used for the stated purpose and applicable environmental / other statutory obligations
are duly complied with.
7. This
issues with the approval of the Competent Authority for necessary compliance
by the Development Commissioners.
No. K-43022/7 /2020-SEZ-Part(I