Exporter undertaking Project Exports and Service Contracts Abroad
should Submit Form DPX1, PEX-1 and TCS-1 to the Approving Authority within 30
days of Entering into Contract
[RBI Circular No. 118 dated 26th
June 2013]
Sub: Export of Goods and Services – Project Exports
Attention of Authorized Dealers is
invited to Para B.7 (i) and C.5 (i) of Memorandum of Instructions on Project
and Service Exports (PEM), enclosed to A.P.(DIR
Series) Circular No.32 dated October 28, 2003, in terms of which an exporter
undertaking Project Exports and Service contracts abroad should submit form
DPX1, PEX-1 and TCS-1 to the Approving Authority (AA) i.e. AD Bank/ Exim Bank/
Working Group, within 15 days of entering into contract for grant of post-award
approval.
2. On a review, it has been decided to increase
the time limit and henceforth the exporter undertaking Project Exports and
Service contracts abroad should submit form DPX1, PEX-1 and TCS-1 to the
Approving Authority (AA) i. e. AD Bank / Exim Bank / Working Group, within 30
days of entering into contract for grant of post-award approval.
3. All other instructions issued in terms of PEM,
notified vide A. P. (DIR Series) Circular No. 32 dated October 28, 2003, shall
remain unchanged.
4. Authorized Dealers may bring the contents of
this circular to the notice of their exporter constituents and customers
concerned.
5. The Directions contained in this circular have
been issued under sections 10(4) and 11(1) of the Foreign Exchange Management
Act (FEMA), 1999 (42 of 1999) and are without prejudice to permissions /
approvals, if any, required under any other law.