Radiation Monitors
Installation Deadline for Un-shredded Scrap at Designated Ports Extended by
Three More Months to 31 March 2020
[DGFT Public Notice No. 49/(2015-2020) dated 24 December 2019
Effect of this Public Notice: The period for installation and operationalisation of Radiation Portal Monitors and
Container Scanner in the designated ports is extended up to 31.03.2020.
Subject: Amendment in
Para 2.54 of the Handbook of Procedures, 2015-2020.
In
exercise of powers conferred under paragraph 2.04 of the Foreign Trade Policy,
2015-2020, the Director General of Foreign Trade hereby amends sub-para (v)(ii)
of Para 2.54 of the Handbook of Procedure (2015-20) and extends the deadline to
install and operationalize Radiation Portal Monitors and Container Scanners upto 31.03.2020. Such sea ports which fail
to meet the deadline will be derecognised for the
purpose of import of un-shredded metallic scrap w.e.f 01.04.2020.
[Issued from
No.01/89/180/53/AM-01/PC-2 (8)/ P - 9348]