7 Ultra Mega Power Projects and 106 Mega Power Projects Get Import
Duty Relief
Seven Ultra Mega Power Projects and 106 mega power
projects will not have to pay higher duty for importing equipment.
The Finance Ministry has notified a new duty
structure that prescribes an effective duty of over 22 per cent, including
education cess.
However, this new duty will not be imposed on ultra mega power projects, mega power projects and
expansion of existing mega projects which had received certificate of approval
from the Power Ministry till July 19, 2012, the date on which the Cabinet took
the decision.
Power Secretary P. Umashankar
says: “There is a list of projects given mega status or provisionally declared
as a mega project. These will not be affected.
But any other project beyond this list will have to
pay duty as per Government notification.”
Ultra Mega Power
Projects to Remain Unaffected
Mundra (Tata Power)
Sasan (Reliance Power)
Krishnapattnam (Reliance Power)
Tilayaa (Reliance Power)
Surjuga (Yet to be awarded)
Bedabahal (Yet to be awarded)
Cheyyur (Yet to be awarded)
Import Duty
Basic
Customs Duty 5%
Countervailing
duty 12%
Special
Additional Duty 4%
Total
effective duty (including education cess) 22.85%
Exempted projects
The list of exempted projects includes 111 mega
projects with permanent certificate and two with provisional ones. The
provisional approval holders have been given three months to convert to
permanent status, the official added. All these mega projects are expected to
take care of capacity addition requirements up to the end of 12th Plan.
Earlier, power equipment for projects with capacity
over 1,000 MW were exempt from basic Customs duty while those for projects with
capacity of less than 1,000 MW attracted basic Customs duty of five per cent.
This was done at a time when there was not enough capacity for ultra mega power projects (project with minimum capacity of
4,000 MW). Power producers such as NTPC and Tata Power say the imposition of
the Customs duty will increase the project cost.
Capacity addition
A senior NTPC official said, “The equipment that we
will buy for our future projects will be more expensive. There would be no
change for the moment.’’
At the same time Tata Power said: “The easy import
of equipment for power projects has been a large contributor to the capacity
addition in the 11th Plan, with almost 50 per cent of additional coal-based
capacities depending on imported equipment.
Added Customs duties will curb the import of
superior technology products that are already high priced, thus, hindering the
advancement of the sector.”
[Source:
The Hindu Business Line dated 11 September 2012]