Exclusive Subsidy Policy for Urea Produced through Coal Gasification
by Talcher Fertilizers Limited (TFL) Approved
The Cabinet Committee on Economic Affairs, chaired by Prime
Minister Narendra Modi, has given its approval for the proposal of the Department
of Fertilizers for the formulation of exclusive subsidy policy for Urea produced
through coal gasification route by Talcher Fertilizers
Limited (TFL) on 20 April 2021.
Objectives
Considering the strategic energy security and urea self-sufficiency
of the country, looking into the country's vast coal reserves, it has been decided
go ahead with Talcher Fertilizer Limited plant based on
coal gasification technology. The project shall improve availability of fertilizer
to farmers thereby boosting development of eastern region
and will save transport subsidy for supply of urea in eastern part of the country.
It would assist in reducing Urea imports to the tune of 12.7 LMT per annum leading
to savings in foreign exchange.
The project will also give a boost to 'Make in India' initiative
and AtmaNirbhar' campaign and would help development of
infrastructure like roads, railways water, etc. providing major boost to economy
in the eastern part of the country including promoting ancillary industry. The project
will also provide New business opportunity in form of ancillary
industries in the catchment area of the project.
Coal gasification plants are strategically important as coal
prices are non-volatile and coal is abundantly available. Talcher
plant shall also reduce dependence on important Natural Gas for production of urea
leading to reduction in LNG import bill. The gasification process adopted in Talcher unit is a Clean Coal Technology giving negligible SOx, NOx and free particulate emissions as compared to directly
coal fired processes.
Background
Talcher Fertilizers Ltd. (TFL) is a Joint Venture Company of four
PSUs namely Rashtriya Chemicals & Fertilizers (RCF),
GAIL (India) Ltd. (GAIL), Coal India Ltd. (CIL) and Fertilizer Corporation of India
Ltd. (FCIL) which was incorporated on 13th November, 2015. TFL is reviving the erstwhile
Talcher plant of Fertilizer Corporation of India Ltd.
(FCIL) by setting up a now greenfield Urea Plant with the installed capacity of
12.7 Lakh Metric Ton per annum (LMTPA). The estimated project cost of the TFL Urea
project is 13277.21 Crore (+/-10%).