Guidelines for early Resolution of Stuck Public Private Partnership (PPP)
Projects at Major Ports
Background
In the past decade, Government of
India invited private investment into Major Port Sector and several projects were
awarded under Design, Built, Finance, Operate & Transfer (DBFOT) basis across
the Major Ports in the country. Since the implementation of first PPP project at
Major Port in 1997, significant progress has been made through this method of implementation.
Notable benefits including private investment, capacity addition and operational
efficiency has contributed to the growth of the sector. Currently, 34 projects of
over INR 27,000 crore are operational and 25 projects of over INR 14,000 crore are
under implementation. The operational projects have added a capacity of around 350
MTPA at Major Ports.
Under Asset Monetisation,
there is clear pipeline of 31 projects of Rs. 14,500 Cr.
to be awarded by 2025. Apart from current pipeline of 31 projects under NMP, additional
50 projects (of value ~INR 27,500 crore) have been identified for offer under PPP.
Out of these 50 projects, 14 projects (~INR 2,400 crore) are envisaged to be offered
in FY 2022-23.
In order to encourage private investment
in the Major Port sector and standardise the diligence
process for implementation of such projects and encourage EoDB,
the Ministry has undertaken many initiatives in terms of preparation of policies/
guidelines.
With the aim to reduce arbitrations and litigation in the sector, new Model
Concession Agreement (MCA) was launched by the Minister of MoPSW
on 21st November 2021. The new document provides clarity on responsibilities
and obligations of parties along with remedial measures in case of change in law.
Apart from new MCA, new Tariff Guidelines have been issued with the focus on flexibility
to PPP player to fix tariffs as per market dynamics, provide level playing field
for competition between private terminals at major port and private port, facilitate
better utilization of the capacity and introduce differential royalty rate to promote
coastal shipping and transshipment
Despite all the policy level initiatives
to mitigate the possibilities of litigation and encourage EoDB
and due diligence and caution at the time of conceptualizing these projects from
various perspectives, the survival of some of the projects is at risk due to various
reasons like aggressive bidding and optimistic projections with regard to volumes
& charges, unforeseen dynamic changes in the business and absence of flexibility
to overcome such dynamic changes in the Concession Agreements that were either not
foreseen or are beyond the control of the collaborating partners, i.e., the Concessionaire
and the Concessioning Authority.
The Guidelines
The Ministry of Ports, Shipping
& Waterways has finalized the guidelines for dealing with Stressed Public Private
Partnership (PPP) Projects at the Major Ports on 10 May 2022.
These guidelines have been framed for:-
i.
Projects which became stressed
during construction stage, i.e., Pre-COD stage i.e. where the work has stopped due to inability of Concessionaire
to continue with the execution of the project because of the reasons inter-alia
aggressive bidding and the optimistic projections with regard to volumes & charges,
unforeseen dynamic changes in their business; and
ii.
Projects, both at Pre-COD and
Post-COD stage, which became stressed due to borrowings being categorized by the
lenders to the projects as NPA and/or lenders have approached NCLT for recovery
of their dues, i.e., the PPP projects undertaken
by the Major Ports where the work has stopped due to inability of Concessionaire
to continue with the execution of the project on account of borrowings of the Concessionaire
having been categorized by lenders as NPA and / or proceedings initiated against
it before the NCLT under the Insolvency and Bankruptcy Code 2016 or under Section
241(2) of the Companies Act 2013.
Mechanism for Resolution of Stressed Projects:
1.
In case of the projects which
became stressed during construction stage i.e., Pre-COD stage, the Concessioning Authority would pay to the Concessionaire or to
the lenders of the Concessionaire (as the case may be), as full and final settlement
for taking over the useful assets created by the Concessionaire, an amount equal
to the lower of the following sums
a.
the value of the work done by
the concessionaire in accordance with the Concession Agreement and found useful
by the major port (i.e. the Concessioning Authority);
or
b.
90% of Debt Due as defined in
the Concession Agreement; or
c.
Any other amount as may be
mutually agreed in writing between the Concessioning Authority
and the Concessionaire as per the relevant provisions
of Model Concession Agreement (MCA) 2021.
2.
Projects which became stressed
both at Pre-COD and Post-COD stage, due to borrowings being categorized by the lenders
to the projects as NPA and/ or lenders have approached NCLT for recovery of their
dues, i.e., the PPP projects undertaken by the Major Ports where the work has stopped
due to inability of Concessionaire to continue with the execution of the project
on account of borrowings of the Concessionaire having been categorized by lenders
as NPA and / or proceedings initiated, the due process before the NCLT under the
Insolvency and Bankruptcy Code 2016 or under Section 241(2) of the Companies Act
2013 will be followed.
The Benefits of the new Guidelines
The aim of the guidelines is to
facilitate revival of the projects falling in the category of stressed projects.
These guidelines will pave the way for resolution of the cases under arbitration.
The port asset is likely to be put to use through re-bidding. This will definitely
result in unlocking the blocked cargo handling capacity of approximately 27 MTPA
thereby creating better trade opportunities for the prospective investors and Port
Authority will start generating revenue. It will repose confidence in the investors/
concessionaires and also generate employment opportunities.
Some of the long standing disputes
on stressed assets at various major ports that may see early resolution are:
i.
Development
of 13th Multipurpose Cargo (Other than Liquid/ Container Cargo) Berth on BOT Basis
at Deendayal Port (1.50 MTPA approx.)
ii.
Development
of 15th Multipurpose Cargo Berth at Kandla
at Deendayal Port (1.50 MTPA approx.)
iii.
Offshore Container
Terminal (OCT) at Mumbai Port (9.60 MTPA approx.)
iv.
Construction
of NCB-II at VOC Port (7.00 MTPA approx.)
v.
Berth EQ-1A
at Visakhapatnam Port (7.36 MTPA approx.)
On this occasion, Sarbananda Sonowal, Union Minister for Ports,
Shipping and Waterways stated that “These Guidelines will facilitate for early resolution
of various issues and revival of stressed projects along with unlocking the immense
potential of those projects resulting in creation of more trade and job opportunities.”