India Prepares for a Change in Electricity Sector through Proposed Electricity
(Amendment) Bill 2020
R. K Singh, the Minister of State (i/c) for Power & MNRE, on 25 June 2020, held a Press Meet
through Video Conferencing and underlined the importance of proposed reforms in
the power sector, dispelling doubts and misinformation. He stated that the reforms
are steps in the direction of making the sector consumer centric as we are all here
to serve them. Mr. Singh said, “ We are not taking away
any powers of States in appointment of members and chairpersons of State Electricity
Regulatory Commissions (SERCs), and the proposed reforms are aimed at promoting
more transparency."
While giving clarity on electricity tariff fixation,
the Union Power Minister stated that the powers of tariff fixation remains with
SERCs. He emphasised that proposed power reforms are aimed
at introducing transparency and accountability to protect the interest of consumers
and ensuring healthy growth of the power sector. He also mentioned that there is
no restrictions on States for providing subsidy as States can give as much subsidy
as they want but they must pay it upfront through Direct Benefit Transfer (DBT)
so that Discoms remain healthy and are able to maintain
and improve distribution infrastructure like transformers and distribution lines,
pay for power purchased and are able to provide quality electricity to the people.
It may be stated that Electricity is one of the
most critical components of infrastructure which is essential for sustained growth
of the economy of the country. While we have made significant improvements in the
electricity generation and transmission segments, the distribution segment, having
achieved 100% village electrification and near-universal access to electricity,
is beset with problems of operational inefficiencies, liquidity, and financial solvency.
In this regard Ministry of Power had prepared a draft proposal for Amendments in
Electricity Act 2003 in the form of draft Electricity (Amendment) Bill 2020 with
the following broad objectives –
•
Ensure consumer centricity
•
Promote Ease of Doing Business
•
Enhance sustainability of
the power sector
•
Promote green power
However, some canards and misconceptions are being
spread regarding some of the proposed amendments to the Electricity Act. It is important
to place the correct position pertaining to them.
Misconception 1: Transfer the power of appointment
to SERCs from State to Central Government
There is no proposal to take away the power of
appointment of Members/Chairpersons of State Electricity Regulatory Commissions
from the State Governments. As per the draft circulated the appointments of Members/Chairpersons
of the State Electricity Regulatory Commissions will continue to be made by the
State Governments. The Selection Committee currently has equal number of members
from the Central and State Government – one member from Central Government and one
from State Government. The proposed Selection Committee in the draft Bill also has
equal number of members from the Central and State Governments as earlier. The only
difference is that instead of the of the Selection Committee
being presided over by a retired Judge of the High Court, it is proposed that the
committee be headed by a sitting Judge of the Supreme Court. Instead of multiplicity
of Selection Committees, there be one Selection Committee for drawing up of panels
for the vacancies in the Central Electricity Regulatory Commission and State Electricity
Regulatory Commissions. The appointments will continue to be made by Central Government
for the Central Electricity Regulatory Commission and by the State Governments for
the State Electricity Regulatory Commissions as before. The reason for this proposed
amendment was that currently every State had to constitute a separate Selection
Committee for each fresh vacancy and this took time. In some cases the time taken
for appointment was up to 2 years leading to disruption of work of the Regulatory
Commission. Regulatory Commissions are the fulcrum around which the Power sector
revolves. Delay were deleterious for the various stake holders such as consumers,
Discoms, and generators etc. However, based on the suggestions
received, the Central Government is now considering to continue with the existing
separate Selection Committees for each state – but make them Standing Selection
Committees so that there is no need for constituting them afresh every time a vacancy
occurs. The Selection Committee will continue to have equal number of members from
the State and Central Governments, as earlier with the only difference that it will
now proposed to be presided by the Chief Justice of the High Court of the state.
Misconception 2: DBT is against the interests of
consumers
Another misconception is that the proposed provisions
for introducing the system of Direct Benefit Transfer (DBT) of subsidies is inimical
to the interest of the consumers especially the farmers. It has been argued that
if the State Government is not able to pay the subsidies on time, the electricity
supply to the consumers may get disconnected. This is baseless. As per Section 65, of the Electricity
Act, 2003, the State Government is required to pay the amount of subsidy in advance
to the distribution companies. The subsidy is now being proposed to be given into
the account of the consumers maintained by the Distribution Companies through DBT.
It is being provided in the new Tariff Policy that the electricity supply shall
not be discontinued even if the State Government is unable to pay the subsidy in
time or even if the State Government fails to pay the subsidy for 3 to 4 months.
Therefore, the consumer's interest will be duly protected. It is, of course, expected
that the State Government pay the subsidy in advance to the DISCOM/consumers as
provided for in the law. It may be noted that the Direct Benefit Transfer will be
beneficial for both the State Governments and as well as Distribution Companies.
It will be beneficial for the State Government because it will ensure that the subsidy
reaches the people who are actually entitled and the State Government gets clear
accounts of the amount given as subsidy. It will benefit the distribution company
by making sure that the subsidies due are received as per the number of beneficiaries.
It may be noted that Government of India have implemented Direct Benefit Transfer
for 419 Schemes pertaining to 56 Ministries with cumulative savings of Rs. 1.70 lac crore.
Misconception 3: Power to
set retail power tariff is being transferred from State to Central Government
Another misconception is that currently the State
Governments fix tariff for retail supply of electricity to consumers and this is
proposed to be taken over by the Central Government. This is again absolutely baseless.
Presently, the tariff is determined by the State Electricity Regulatory Commission
and no change has been proposed in the present arrangement.
The other major amendments proposed in the Electricity
Act are as follows.
Sustainability
(i)
Cost reflective Tariff: To
eliminate the tendency of some Commissions to provide for regulatory assets, it
is being provided that the Commissions shall determine tariffs that are reflective
of cost so as to enable Discoms to recover their costs.
It is estimated that the total regulatory asset, ie revenue
due to a Discom but not collected because appropriate
tariff increase was not given, in the country is about Rs.
1.4 lakh crore.
(ii)
Establishment of adequate
Payment Security Mechanism for scheduling of electricity - It is proposed to empower
Load Dispatch Centres to oversee the establishment of
adequate payment security mechanism before dispatch of electricity, as per contracts.
Late payment of dues of generating and transmission
companies have reached unsustainable levels. As of 31.03.2019, the payables to the
Gencos and Transcos were Rs. 2.26 lakh crore. This not only impairs the finances of the
Gencos and Transcos making it
difficult for them to pay for fuel and other expenses but also has a debilitating
impact on the Banks. If liquidity is not maintained, the power sector can collapse.
Thus, it is in our collective interest to put in place systems for ensuring timely
payments. That is why it is being provided that electricity shall not be scheduled
or despatched unless security of payment has been established.
Ease of Doing Business
(iii)
Cross Subsidy: At present,
the Act provides for the State Commissions to progressively reduce cross subsidies.
Despite the requirement of the Tariff Policy to reduce cross-subsidies to within
20% of average cost of supply, they are in excess of 50% in some States making industries
uncompetitive. The Bill provides for the SERCs to reduce cross subsidies as per
the provisions of the Tariff Policy. The Tariff Policy is prepared after consultation
with the all stakeholders and the views of the State Governments are taken into
consideration before finalising its provisions. It is
noteworthy that there is no proposal to eliminate cross subsidy.
(iv)
Establishment of Electricity
Contract Enforcement Authority: CERC and SERCs do not have powers to executetheir orders as decree of a civil court. An Authority
headed by a retired Judge of the High Court is proposed to be set with such powers
including but not limited to powers of attachment and sale of property, arrest and
detention in prison and appointment of a receiver to enforce performance of contracts
related to purchase or sale or transmission of power between a generating company,
distribution licensee or transmission licensee. This will enhance sanctity of contracts
and spur much needed investment in the power sector.
Renewable and Hydro Energy
(v)
National Renewable Energy
Policy: For environmental reasons, it is in our long term interest to promote green
power. India is a signatory to the Paris Climate Agreement.It
is therefore proposed to have a separate policy for the development and promotion
of generation of electricity from renewable sources of energy.
(vi)
It is also proposed that a
minimum percentage of purchase of electricity from hydro sources of energy is to
be specified by the Commissions.
(vii)
Penalties: It is being further
proposed to levy penalties for non-fulfilment of obligation to buy electricity from
renewable and/or hydro sources of energy.
Miscellaneous
(viii) Strengthening of the Appellate Tribunal (APTEL): It is proposed to
increase the strength of APTEL its strength of Members, apart from the Chairperson,
to at least seven to facilitate quick disposal of cases. It may be noted that there
are a large number of cases pending in APTEL at present. To be able to effectively
enforce its orders, it is also proposed to give it the powers of High Court under
the provisions of the Contempt of Courts Act.
(ix) Penalties: In order to ensure compliance of the
provisions of the Electricity Act and orders of the Commission, section 142 and
section 146 of the Electricity Act are proposed to be amended to provide for higher
penalties.
(ix)
Cross border trade in Electricity:
Provisions have been added to facilitate and develop trade in electricity with other
countries.
(x)
Distribution sub-licensees:
To improve quality of supply, an option is proposed to be provided to Discoms to authorise another person
as a sub-license to supply electricity in any particular part of its area, with
the permission of the State Electricity Regulatory Commission.
It may be noted that provisions relating to Distribution
Franchisee already exist in the Act and are being successfully used by Distribution
Companies to improve performance and enhance efficiencies. These are enabling provisions
for use by DISCOMs / States which want to give out some areas to Franchisees / Sub-licensees.
It has been ensured that Distribution Sub Licensee remains under regulatory control
and jurisdiction to protect interest of consumers.