MOEF Rebuts Claim
of Environment Hurdles Blocking Projects
In the wake of the nationwide power outages over the last two
days, a section of the media has reported that one of the main reasons for the
failure of the power grades have been power projects, which are said to have
been “stalled” due to want of Environmental Clearance (EC). This is factually
incorrect. The status is as follows:
NTPC Bijapur Karnataka is said to have
been stalled due to lack of environmental clearance. The fact is EC was granted
on 25 January 2012.
Essar Madhya Pradesh is said to have
been stalled due to lack of EC, but EC was granted as early as 20 April 2007.
The same applies to Reliance Power Chitrangi Madhya
Pradesh where EC was granted on 28 May 2010. The Essar
plant is already in operation, although final Forest Clearance (FC) for both
these projects is pending.
NHPC Dibang valley has been violently
opposed by the local people, and public hearing has been postponed 5 times due
to public unrest, although initial Terms of Reference (TORs) were issued on 17
August 2009. Further Dibang involves diversion of
5056 hectares of forest land-a massive extent of land which has to be carefully
studied. With regard to the NHPC Middle Subanshri
project, even the application for EC is yet to be received; Jaypee
Lower Siang was granted TORs in 1 January 2007. But public unrest has not
enabled the State Government to conduct public hearing to proceed further.
NPCIL Mithvirdi Gujarat far from being
stalled due to lack of EC, even the application for EC has not been received at
MoEF.
Saurashtra Coal Based is said to be
stalled for want of FC but no application for FC has been received in the
Ministry.
The Cheemei gas based TPP by Kerala
State Industrial Corporation was considered for EC but postponed, because the
promoters were not even sure about the blend of natural gas and RLG which they
proposed to use for the plant. They were told to put their plan together and
revert to MoEF.
With regard to environment and forest clearances for power plants,
the following are the facts, as brought out by an independent study done by the
Centre for Science and Environment in 2011. The 11th Five Year Plan has
projected a target of 50,000 MW of additional thermal power capacity; the 12th
Plan asks for 100,000 MW. Thus the total projection of power requirement for
the 12th Five Year Plan is 100,000 MW. In the past 5 years, upto
2011, the MoEF has granted environmental clearance to
210,000 MW of power- that is 60,000MW more power than has been proposed until
2017. In most cases including coal and thermal power projects, clearances given
by MoEF far exceed targets, and even capacity
projected for the future. Figures and statistics which bear out this statement
are available for every sector.
Further, MoEF has reviewed existing
procedures to ensure that in cases where clearances are granted, there is no
undue delay hardship or loss caused to the economy. It has been directed that
both forest and environmental clearances should be simultaneously processed, in
order to avoid delay. However, the actual EC is only handed over after the
final forest clearance and wildlife clearance where necessary are given. With
regard to forest clearance, upto 40 ha forest land
may be cleared at the regional level itself, and it is only for much larger
tracts of forest land that the matter is processed at MoEF.
Four new regional offices in addition to the existing offices are being opened
to facilitate the working of the Ministry, and also the Ministry has been
strengthened by a GIS satellite data base-both to work on improving forest
cover, as also to facilitate gathering of information for faster clearance.
It is reiterated that the best interests of the country require
that utmost importance is given to considerations of protecting, nurturing,
preserving and saving the environment.
[Source: Ministry of Environment and Forests, PIB Press Release
dated 1st August 2012]