More Local Powers for Border Infra
Posted On: 18 MAY 2020 5:11PM by PIB Delhi
Government has accepted and implemented three
important recommendations of Committee of Experts (CoE)
under the Chairmanship of Lt General D B Shekatkar (Retd) relating to border Infrastructure. These were related
to speeding up road construction, leading to socio economic development in the
border areas.
On the matter related to creating border infrastructure,
the Government has implemented recommendation of CoE
to outsource road construction work beyond optimal capacity of Border Roads Organisation (BRO). It has been made mandatory to adopt
Engineering Procurement Contract (EPC) mode for execution of all works costing
more than Rs 100 crore.
The other recommendation relating to introduction of
modern construction plants, equipment and machinery has been implemented by
delegating enhanced procurement powers from Rs 7.5
crore to Rs 100 crore to BRO, for domestic and
foreign procurements. Border Roads has recently inducted Hot-Mix Plant 20/30
TPH for speedier laying of roads, remote operated hydraulic Rock Drills DC-400
R for hard rock cutting, a range of F-90 series of self-propelled
snow-cutters/blowers for speedier snow clearance.
New Technology like blasting technology for precision
blasting, use of Geo-Textiles for soil stabilisation,
cementitious base for pavements, plastic coated aggregates for surfacing, is
also being used to enhance the pace of construction. With the empowerment of
field officers through enhanced delegation of financial and administrative
powers, there has been significant improvement in faster financial closure of
works.
The land acquisition and all statutory clearances like
forest and environmental clearance are also made part of approval of Detailed
Project Report (DPR). Further, with the adoption of EPC mode of execution, it
is mandatory to award work only when 90 per cent of the statutory clearances
have been obtained, implementing the recommendation of CoE
regarding obtaining prior clearances before the commencement of the project.