Power Ministry Issues Guidelines for Battery Storage as part of
Generation, Transmission and Distribution assets, along with Ancillary Services
<Guidelines
No.
23/16/2020-R&R Part (1)/10.03.2022]
The Ministry of Power on March 10, 2022 has issued
Guidelines for Procurement and Utilization of Battery Energy Storage Systems as
part of Generation, Transmission and Distribution assets, along with Ancillary
Services.
• The objectives to provide these guidelines are as
followed:
1. To facilitate procurement of BESS, as part of
individual RE power projects or separately, for addressing the
variability/firming power supply / increasing energy output / extending the
time of supply from an individual RE project or a portfolio of RE projects,
augmentation of existing RE Projects and/or to provide ancillary, grid support
and flexibility services for the grid.
2. To facilitate procurement of BESS for optimum
utilization of transmission and distribution network.
3. To ensure transparency and fairness in procurement
processes/ and to provide for a framework for an Intermediary Procurer as an
Aggregator / Trading licensees / Implementing Agency for the
inter-state/intra-state sale-purchase of power.
4. To provide standardization and uniformity in processes
and a risk-sharing framework between various stakeholders, involved in the
energy storage and storage capacity procurement, thereby encouraging
competition and enhanced bankability of the Projects.
• The Applicability of the guidelines are as followed:
These Guidelines are being issued under the provisions of
Section 63 of the Electricity Act, 2003 for procurement of energy from BESS by
the ‘Procurers’, through competitive bidding, from grid- connected Projects to
be set up on “Build-Own-Operate” or “Build-Own-Operate-Transfer” basis, with
following minimum project size and bid capacity requirements:
(i)
For Intra-State
Projects: Minimum individual project size of power rating of 1MW and above with
suitable energy rating based on application at one site with minimum bid
capacity of 1MW; and
(ii) For Inter-State Projects: Minimum individual project capacity
of 50 MW and above with suitable energy rating based on application at one site
with minimum bid capacity of 50 MW at the minimum voltage level as specified by
the extant CERC regulations/Detailed Procedure.
The provisions of these Guidelines shall be binding on
the BESSD /Procurer/ Intermediary Procurer/End Procurer/Implementing Agency and
the Authorised Representative of the Procurer. The
process to be adopted in event of any deviation proposed from these Guidelines
is specified in Clause A, Section V of these Guidelines.
[Resolution No. 23/16/2020-R&R Part (1)]