Solar Power
Majors Get $3-billion Shock from Supreme Court Order
A Supreme Court order that requires overhead power lines to be taken
underground in the habitats of a critically endangered bird is likely to hurt
the financial viability of solar projects in Rajasthan and Gujarat. Developers
estimate the total cost to change the existing overhead wires to underground
cables at Rs 22,000 crore, requiring a tariff hike of
10-15% if they have to bear this entire cost, industry insiders said.
The companies developing projects in
the region are among the biggest in the business, including Adani Green, ReNew Power, Hero Future Energies, SB Energy, Greenko and state-run NTPC.
The solar industry association now
plans to approach the Supreme Court, seeking at least a partial relief on the
order, as laying high-voltage cable underground is not feasible, they said.
The two states, which house many solar power
projects, including the world’s largest at Bhadla in
Rajasthan’s Jodhpur district, account for about a quarter of the total solar
power production in India. The regions that house the projects are also
habitats of the Great Indian Bustard (GIB), a tall and heavy bird with a
wingspan of more than two metres. Only around 150 of
these birds exist, according to wildlife experts, and some 15% die every year
due to electrocution.
On January 9, ET reported the National
Green Tribunal’s order directing the Centre and the two states to install bird
diverters on all existing power lines within four months.
Feasibility Report for Change
NGT also directed laying all new
transmission lines underground to prevent more GIB fatalities. However, last
month, the apex court ordered that all transmission lines, including existing
ones, be made underground.
“If the court does not review the decision and
if (it) is implemented in toto, then it would bleed
the industry and make the projects unviable,” said a top executive at one of
the affected companies. “Further, it is noteworthy to mention that no further
projects would be feasible to be set up in Rajasthan, which is the most
promising area in India for the growth of solar.”
As per the discussions at an
interaction last week between the ministry of new and renewable energy (MNRE)
and solar industry representatives, low-voltage lines of 33 kV will cost Rs 84 lakh per kilometre to take
underground, while for high-voltage lines of 220 kV, expense will be as high as
Rs 28.8 crore a km. More than 2,500 kilometres of cables, including both high- and low-voltage,
have to be laid underground as per the court ruling.
Emails to SB Energy, ReNew, Adani Green, Acme Solar, Hero Future Energies and
NTPC were not answered till press time on Monday. MNRE officials and
representatives from the Gujarat and Rajasthan governments also did not respond
to queries.
Tata Power declined to comment.
Priority & Potential Areas
Based on a 2019 report by the Wildlife
Institute of India, the flight path of the birds — which are only seen in India
and some parts of Pakistan — has been divided into ‘priority’ and ‘potential’
areas.
While the priority area will affect
the solar projects by Adani Green and SoftBank-backed
SB Energy, the potential area, which demarcates parts of west Rajasthan, will
cover the 5,700-hectare Bhadla Solar Park.
Other players such as Tata Power
Renewables, O2, Vena and Greenko will also be
affected due to the geographical expanse of the potential area, which stretches
from the western border of Rajasthan to Barmer,
Jodhpur and Bikaner.
Wildlife conservationists said that if
implemented in a timely manner, the steps ordered by the top court would reduce
the death of these birds caused by powerline
collisions. “(This) should become the norm for greener power lines across all
bird migratory pathways within protected areas and near wetlands,” said Yadvendradev Jhala, dean,
Wildlife Institute of India.
Technical & Cost Challenges
There are technological and implementation
challenges in laying underground high voltage transmission lines, said Shekhar Dutt, director-general at
the Solar Power Developers Association. “It is also felt there is very little
impact of overhead transmission lines on GIB in potential areas, so high-tech
bird diverters can be selected in consultation with experts which can be very
effective," he added.
Another industry executive, who did
not want to be named, said the Rs 22,000-crore cost
figure might be a conservative estimate, as it accounted for only laying
underground 220 kV lines. “There are lines that go up to 400 kV and above that
haven’t yet been taken into account,” this executive said.
State and central governments will
bear some costs of the undergrounding, as they have "a duty cast to
preserve the endangered species,” as per the court order. They may pay for the
transmission lines between the substations and end consumers, but developers
will still bear the brunt — between the solar plant and substation, which makes
up nearly 80% of the entire system.
While cost will go up, developers will
get relief due to the ‘change in law’ provision in their power purchase
agreements (PPAs), allowing them to raise tariffs. But distribution companies
are likely to face challenges in passing the higher cost to consumers.
“Although existing projects will have
a cushion of change in law and force majeure provisions of the PPA to mitigate
risks, those claims will not be uncontested, considering the stakes involved,”
said Aditya K Singh, an associate partner at Link Legal.