Last Date for Installation of Radiation Monitors for Un-shredded Scrap at Designated Ports Extended by Three More Months till 30 June 2019

[DGFT Public Notice No. 80/(2015-2020) dated 22 March 2019]

Effect of this Public Notice: The period for installation and operationalization of Radiation Portal Monitors and Container Scanner in the designated ports is extended up to 30.06.2019

Subject: Amendment in Para 2.54 of the Handbook of Procedures, 2015-2020.

In exercise of powers conferred under paragraph 2.04 of the Foreign Trade Policy, 2015-2020, the Director General of Foreign Trade hereby amends sub-para (v)(ii) of Para 2.54 of the Handbook of Procedure (2015-20) and extends the deadline to install and operationalize Radiation Portal Monitors and Container Scanners by 30.06.2019. Such sea ports which fail to meet the deadline will be derecognised for the purpose of import of un­ shredded metallic scrap w.e.f 01.07.2019.

[Issued from No. 01//89/180/53/AM-01 /PC-2 (B)/ e- 2382]