₹4,288-Crore
Second Container Terminal at Kamarajar Port to Boost EXIM
Trade and Maritime Connectivity Approved
Ø Cabinet approves development
of the Second Container Terminal at Kamarajar Port Limited
under Public Private Partnership (PPP) Mode on Design, Build, Finance, Operate and
Transfer (DBFOT) Basis
·
The Cabinet Committee on Economic Affairs has approved
the development of a Second Container Terminal at Kamarajar
Port, Tamil Nadu, under the PPP model on a DBFOT basis, at an estimated investment
of ₹4,288.26 crore.
·
The project envisages a 900-metre-long terminal
with an annual handling capacity of 2 million TEUs, to be developed in two
phases: 1.1 million TEUs in Phase I and 0.9 million TEUs in Phase II.
·
With a design draft of 18 metres,
the terminal will be capable of handling large container vessels of up to 24,346
TEUs and 400 metres in length, strengthening direct connectivity
with international shipping routes.
·
The project will be implemented through global competitive
bidding for a 40-year concession period, including 48 months of construction.
Phase I is targeted for completion within 24 months and Phase II within 48 months.
·
An additional ₹450 crore will be incurred by Kamarajar Port for dredging, separately from the PPP project
investment.
·
The new terminal will support growing EXIM cargo from Tamil
Nadu and the southern hinterland, particularly automobiles, engineering goods, electronics,
chemicals and other manufactured products.
·
The project is expected to reduce dependence on foreign
transshipment hubs, lower feedering costs, improve maritime
logistics efficiency and strengthen India's East Coast container-handling capacity.
·
It is expected to generate approximately 750 direct
and indirect jobs during construction and around 800 jobs during operations.
·
The project aligns with Maritime India Vision 2030 and
Maritime Amrit Kaal Vision 2047 and will be financed by the selected concessionaire,
with no financial implication for the Government of India.
[ABS News Service/26.11.2026]
The Cabinet Committee on Economic Affairs
chaired by the Prime Minister Narendra Modi, has approved the proposed project for
development of the Second Container Terminal at Kamarajar
Port Limited (KPL) under the Public Private Partnership (PPP) mode on a Design,
Build, Finance, Operate and Transfer (DBFOT) basis, at an estimated project cost
of Rs.4,288.26 crore, including GST. The project envisages the development of a
900-metre-long container terminal with a design draft of 18 metres and an annual
container-handling capacity of 2.0 million Twenty-foot Equivalent Units (TEUs),
to be implemented in two phases.
Expenditure involved:
The estimated project cost of the PPP
component is Rs.4,288.26 crore, including GST, comprising Rs.2,429.32 crore for
Phase I and Rs.1,858.94 crore for Phase II. The investment is to be arranged by
the selected concessionaire under the DBFOT model. The project proposal separately
indicates an estimated dredging cost of Rs.450 crore to be borne by KPL.
Details:
(i) The project envisages development of a 900-metre-long
Second Container Terminal with a berth width of 30 metres and an annual container-handling
capacity of 2.0 million TEUs. The terminal will be developed in two phases: Phase
I with a capacity of 1.1 million TEUs and Phase II with a capacity of 0.9 million
TEUs.
(ii) The
terminal is designed to handle large container vessels, including vessels of up
to 24,346 TEUs and 400 metres in length overall, with a design draft of 18 metres.
This will strengthen KPL’s ability to handle larger mainline vessels and improve
connectivity with international shipping routes.
(iii) The project is intended to meet the growing demand for containerised
export-import (EXIM) cargo from the Chennai–Ennore industrial
and economic region and the wider southern hinterland. Key cargo-generating sectors
include automobiles and auto components, engineering goods, electronics, chemicals
and other manufactured products.
(iv) KPL
handled 49.08 million tonnes of cargo and 1,008 vessels during FY 2025–26, including
more than 7 lakh TEUs of container traffic. The existing container terminal has
an installed capacity of 0.8 million TEUs per annum and handled approximately 0.7
million TEUs in FY 2025–26, representing utilisation of about 88%.
(v) Container
traffic in India has grown at a compound annual growth rate (CAGR) of about 7% over
the last five years, while KPL’s container traffic has grown at approximately 9.9%
during the same period. The feasibility study projects continued growth in container
traffic in the south-eastern region, supporting the need to augment capacity at
KPL.
(vi) The
project will be implemented on a DBFOT basis for a concession period of 40 years,
including a construction period of 48 months. Phase I is scheduled for completion
within 24 months from the Date of Award of Concession, with commercial operations
commencing in the 25th month. Construction of Phase II will be undertaken from the
25th to the 48th month, with full commercial operations commencing in the 49th month.
(vii) The
estimated project cost is Rs.4,288.26 crore, including GST, comprising Rs.2,429.32
crore for Phase I and Rs.1,858.94 crore for Phase II. The cost is to be financed
by the selected concessionaire through the DBFOT framework. In addition, KPL is
to incur an estimated Rs.450 crore towards dredging, as indicated in the project
proposal.
(viii) The project is proposed to be implemented through a transparent,
open global bidding process. The concessionaire will arrange the required financing
and recover its investment through user charges in accordance with the provisions
of the Concession Agreement and applicable tariff framework.
(ix) The
project is aligned with Maritime India Vision 2030 and Maritime Amrit Kaal Vision 2047. It is expected to strengthen KPL’s position
as a container gateway on India’s East Coast, improve the efficiency of the maritime
logistics chain and support the growth of EXIM trade.
Implementation Strategy and Targets:
The project will be implemented by the
selected concessionaire under the DBFOT model. Phase I, with a capacity of 1.1 million
TEUs, is to be completed within 24 months from the Date of Award of Concession,
and commercial operations are to commence in the 25th month. Phase II, with a capacity
of 0.9 million TEUs, is to be completed by the 48th month, with full commercial
operations commencing in the 49th month. The project proposal also provides for
obtaining environmental and other necessary clearances in a time-bound manner before
the bid due date.
Major Impact:
(i) The additional capacity of 2.0 million TEUs per
annum will strengthen KPL’s ability to accommodate growing container traffic and
provide an additional gateway for EXIM cargo from the industrial clusters of Tamil
Nadu and the adjoining hinterland.
(ii) The
terminal’s design draft of 18 metres and capability to handle large container vessels
are expected to improve international connectivity, facilitate direct calls by mainline
vessels and reduce dependence on foreign deep-water hub ports and associated feedering costs.
(iii) The
project is expected to improve maritime logistics efficiency, support trade and
manufacturing, strengthen the port’s revenue potential and contribute to India’s
maritime competitiveness.
(iv) The
project is expected to generate employment for approximately 750 persons directly
and indirectly during construction and to increase about 800 persons during the
operational phase.
(v) The
project supports the objectives of Atmanirbhar Bharat
by augmenting domestic port capacity and improving logistics support for industries
and original equipment manufacturers in Tamil Nadu, Karnataka, Andhra Pradesh, Telangana
and the adjoining hinterland.
(vi) There
will be no financial implication for the Government of India, as the investment
in the PPP component will be arranged by the selected concessionaire.
Background:
(i)
Kamarajar Port Limited, formerly known as Ennore Port Limited, one of the 12 Major Ports of India and
is wholly owned by Chennai Port Authority under the Ministry of Ports, Shipping
and Waterways. Located on the east coast of Tamil Nadu near the Chennai industrial
and economic region, the port handles a range of cargo, including coal, petroleum,
oil and lubricants, LNG, LPG, containers, automobiles and general cargo.
(ii)
During FY 2025–26, KPL recorded revenue of approximately Rs.1,280 crore and
Profit Before Tax of Rs.924 crore. The port has recorded cargo growth at a CAGR
of 13.64% over the last five years, reflecting the expansion of economic activity
and trade in its hinterland.
(iii) The Chennai–Ennore region is a major industrial
and manufacturing cluster of India. As trade and containerisation expand, additional
container-handling capacity and efficient facilities for larger vessels are required
to support the movement of EXIM cargo from Tamil Nadu, southern Andhra Pradesh and
the wider southern hinterland.