Sri Lanka Terminates US$392 Million Colombo Logistics Hub Project with Chinese Investor, Settled for $22 mn Payment

China Merchants Port Holdings has agreed to terminate its involvement in a planned US$392 million logistics complex at Sri Lanka’s Colombo Port. The settlement provides for repayment of project-related funds and the winding up of the joint venture, ending a development launched in 2023.

·         Project Terminated: China Merchants Port Holdings, its partners and the Sri Lanka Ports Authority (SLPA) have agreed to terminate the South Asia Commercial and Logistics Hub project at the Port of Colombo. The decision was announced on 15 October 2026.

·         Reason for Termination: The parties cited changes in external circumstances, the implementation environment, project timelines and commercial considerations. No single political or geopolitical cause was established.

·         Project Cost: The proposed logistics complex was valued at US$392 million and was launched in April 2023 as a major commercial logistics infrastructure development.

·         Settlement Amount: SLPA will pay US$21.905 million to the project company within 30 days of the settlement agreement. The amount will subsequently be distributed among shareholders according to their ownership interests.

·         Settlement Calculation: The payment was calculated by starting with US$26 million and deducting US$3.9 million in value-added tax and US$195,000 in late-payment charges.

·         Additional Funds: The project company held approximately US$7.85 million in distributable cash as of 31 December 2025, which is also subject to shareholder distribution arrangements.

·         Shareholding Structure:

o    Fortune Centre Group Limited, a wholly owned subsidiary of China Merchants Port Holdings: 70%.

o    Access Engineering, Sri Lanka: 15%.

o    Sri Lanka Ports Authority: 15%.

·         Original Development Plan: The consortium proposed a 50-year concession under a build-operate-transfer (BOT) model, covering the financing, design, construction, development, operation and maintenance of the logistics complex.

·         Impact on Colombo Port: The termination removes the proposed facility from the current development pipeline, leaving the planned additional logistics capacity unrealised under the original consortium.

·         Financial Clarification: The US$392 million project value was the proposed investment cost, not the amount already spent or the compensation payable for termination.

·         Future Prospects: Fresh proposals for developing the site are expected, but no replacement investor, financing arrangement or construction schedule has been confirmed.

·         Scope of Withdrawal: The cancellation applies to this specific logistics hub and its associated agreements. It does not establish that China Merchants Port Holdings is withdrawing from all its investments in Sri Lanka.

 

[ABS News Service/21.10.2026]

Agreement brings development to a close

The Colombo logistics hub project will not proceed under its existing arrangements after China Merchants Port Holdings, its partners and the Sri Lanka Ports Authority agreed to terminate the development.

Announced on 15 October 2026, the decision covers the South Asia Commercial and Logistics Hub, a proposed commercial logistics complex within the Port of Colombo. The termination arrangements cover the shareholders’ agreement, build-operate-transfer agreement and site lease, alongside the orderly closure of the project company.

Changes in external circumstances, the implementation environment and the timetable, together with the parties’ commercial considerations, were cited as reasons for ending the venture. The announcement does not establish a single political or geopolitical cause for the decision.

Settlement separates planned investment from money committed.

Under the settlement, the Sri Lanka Ports Authority will pay US$21.905 million to the project company, South Asia Commercial and Logistics Hub, within 30 days of the settlement agreement.

That payment is to be distributed among the shareholders according to their ownership interests. It is therefore a payment to the joint venture for subsequent distribution, rather than a sum payable entirely to China Merchants.

The settlement calculation starts with US$26 million and deducts US$3.9 million in value-added tax and US$195,000 in late-payment charges.

Separately, the project company held approximately US$7.85 million in distributable cash as at 31 December 2025. That balance is also covered by arrangements for distribution to shareholders.

These amounts must be distinguished from the widely reported US$392 million project value. That figure represented the proposed development’s investment cost; it was neither the amount already spent nor the compensation agreed for termination.

Consortium had planned a major logistics complex

China Merchants participated through its wholly owned subsidiary, Fortune Centre Group Limited, which held 70% of the project company. Sri Lanka’s Access Engineering and the Sri Lanka Ports Authority each held 15%.

The ownership structure combined an international port investor, a local engineering company and the public authority responsible for the port. The joint venture was established to finance, design, construct, develop, operate and maintain the facility under a public-private partnership.

Its responsibilities extended beyond construction to the long-term management of the proposed logistics operation. Terminating the agreements consequently ends both the development arrangements and the operating framework envisaged for the consortium.

The consortium launched the project in April 2023, presenting it as a major addition to Colombo’s commercial logistics infrastructure. At that stage, the development was promoted as South Asia’s largest commercial logistics complex, with a planned investment of US$392 million.

The proposed concession ran for 50 years under a build-operate-transfer model. Its cancellation closes that particular long-term development arrangement; it does not by itself determine what infrastructure will eventually occupy the site.

Commercial implications centre on the unrealised facility

For Colombo’s logistics sector, the immediate consequence is that the proposed complex will not be delivered by the original consortium under the agreed structure.

Commercially, this removes a planned source of additional logistics infrastructure from the current development pipeline. Businesses evaluating future capacity should therefore distinguish the cancelled proposal from facilities already operating at the port.

The financial settlement also provides a route for closing the venture’s outstanding obligations. Repayment, distribution of available funds and deregistration are separate steps from identifying a replacement development.

The termination should not be interpreted as confirmation that China Merchants is withdrawing from every Sri Lankan port investment. The agreements being ended concern this logistics hub and its project company.

Future development requires a fresh arrangement

Reporting on the cancellation indicates that fresh proposals are expected for the logistics development. However, that does not establish that a replacement investor has been selected, financing secured or a new construction timetable agreed.

Any successor proposal would need its own commercial structure, approvals and implementation commitments. Until those are announced, the confirmed development is the termination and settlement of the original venture, rather than the launch of a replacement project.