T-61 – 5th TBM for Mumbai Metro’s Line-3 Arrives at Mumbai Port
Parts of TBM T-61, a Ø6.68m
dual-mode tunnel boring machine, made a touch-down at Mumbai Port this Sunday
after getting shipped from Terratec’s plant in
Guangzhou, China.
This Ø6.68m Earth Pressure Balance (EPB) machine passed factory acceptance testing (FAT) on September 21 and
will be deployed by the J Kumar Infraprojects – China
Railway Tunnel Group JV along with 2 other new dual mode rock TBMs (T-60, T-62) and 2 refurbished TBMs (S-63, S-64) to build twin tunnels on the
line’s 4.94 km package UGC-05 (Dharavi Station – CSIA
T1 TBM receiving shaft) and 4.45 km package UGC-06 (CSIA T1 Station – Marol Naka TBM receiving shaft).
As per the tunneling plan, T-61 will be deployed exclusively
to build the 4687m down-line tunnel between Vidyanagari
– Santa Cruz – CSIA T1 and Sahar Road.